International Rail Freight in Vietnam: Customs Procedures, Documents and Incoterms

International rail freight from Vietnam currently crosses the border at two rail border stations, Dong Dang (Lang Son) and Lao Cai, mainly into China. Goods moving by rail are still declared to customs like ordinary export and import goods.
This guide summarises the routes, documents, suitable Incoterms, procedures at the station and how freight is added to customs value. The most important point: Vietnam and China use different track gauges (1,000 mm and 1,435 mm), so most routes require transshipment.
SUMMARY: INTERNATIONAL RAIL FREIGHT FROM VIETNAM
- Border stations: The two rail border stations are Dong Dang (Lang Son) and Lao Cai.
- Track gauge: Vietnam uses 1,000 mm gauge and China 1,435 mm; only the Dong Dang – Pingxiang route connects directly.
- Transport document: Goods moving within the OSJD bloc use an SMGS waybill.
- Incoterms: Use FCA, CPT, CIP or DAP; FOB, CFR and CIF are for sea and inland waterway transport only.
- Customs value: International freight not already in the price is added to customs value; domestic freight from the interchange station is not.

Rail routes and border stations
Vietnamese railways use a 1,000 mm gauge, while Chinese railways use a 1,435 mm gauge. According to VOV (04/2026), only the Dong Dang – Pingxiang (Bang Tuong) route currently allows a direct connection, and most other routes require transshipment. The Lao Cai route runs on 1 m gauge as far as Ha Khau, and goods heading deeper into China must be moved to another train.
Some capacity benchmarks:
- In 2025, freight carried by international through rail exceeded 1 million tons, up nearly 30% on the previous year (figures from Vietnam Railways).
- The Kep – Dong Dang and Cao Xa – Dong Dang – Pingxiang sections are running close to capacity.
- According to Thanh Nien (07/2023), 8 stations are planned to handle international through trains: Dong Dang, Lao Cai, Yen Vien, Kep, Song Than, Kim Lien, Dieu Tri and Trang Bom. At that time a refrigerated container train from Song Than to Dong Dang took about 72 hours.
The Lao Cai – Hanoi – Hai Phong line on 1,435 mm gauge, nearly 391 km long, is under construction. Before booking, ask the carrier for the departure station, border station, transshipment point and expected transit time for each leg.
Legal framework
- Railway Law 95/2025/QH15, passed by the National Assembly on 27/6/2025 and effective from 01/01/2026, replacing Railway Law 06/2017/QH14.
- The Ministry of Construction manages rail transport after its merger with the Ministry of Transport (the decree on functions took effect on 01/3/2025).
- Customs procedures for international through trains entering and leaving the country are in Articles 69 to 73 of Decree 08/2015/ND-CP, as amended by Decree 59/2018/ND-CP.
- Vietnam is a member of the Organisation for Cooperation of Railways (OSJD). OSJD administers the SMGS Agreement on international rail freight, so goods moving within the OSJD bloc use an SMGS waybill.
Documents for a rail shipment
The commercial documents are the same as for sea freight: contract, commercial invoice, packing list, C/O, and a licence or specialised inspection result if the goods require one. The transport document is a rail waybill issued by the rail carrier, in place of a sea bill of lading.
In addition to the owner’s declaration, the interchange station and the train manager submit documents for the train under Articles 69 and 70 of Decree 08/2015/ND-CP:
- Train entering at a border station: the goods handover certificate (original), the waybill (copy) and the extract of the import cargo manifest unloaded at each station. The documents are submitted as soon as the train arrives at the station.
- Train leaving the country: the extract of the cargo manifest, the waybill and the confirmation of the train formation order. A freight train submits them no later than 1 hour before leaving the station.
The goods description, weight and container numbers on the waybill must match your invoice and declaration, because the cargo manifest extract is prepared from the waybill.
Choosing the delivery term
Incoterms 2020 has 7 rules for any mode of transport (EXW, FCA, CPT, CIP, DAP, DPU, DDP) and 4 rules for sea and inland waterway transport only (FAS, FOB, CFR, CIF). Goods moving by rail should use the first group:
- FCA: the seller delivers the goods to the carrier nominated by the buyer at an agreed place (for example the departure station), and risk passes from that point. The buyer signs the carriage contract.
- CPT: the seller pays freight to the destination, but risk passes when the goods are handed to the first carrier.
- CIP: as CPT, and the seller also buys insurance at the minimum level of Institute Cargo Clauses (A).
Under all three rules, the seller clears the goods for export and the buyer clears them for import. Using FOB or CIF for goods moving by train means choosing from the wrong group of rules.
Rail freight and customs value
For goods imported by rail, the first point of entry is the international through rail station named on the customs declaration (Decree 08/2015/ND-CP as amended by Decree 59/2018/ND-CP). Official Letter 4838/TCHQ-TXNK of 26/7/2019 gives guidance under Article 13 of Circular 39/2015/TT-BTC:
- International freight that the buyer pays to Vietnam Railways at the interchange station, if not already included in the price actually paid, must be added to customs value.
- Domestic freight from the interchange station to the delivery station inland is not included in customs value.
You should ask for a freight invoice that separates the international leg from the domestic leg so you can declare correctly.
C/O for rail shipments
A C/O does not depend on the mode of transport. Goods from China entering via Dong Dang or Lao Cai still use a Form E C/O under ACFTA, or documents under RCEP. Check that the waybill number, name of the means of transport and the port or station of unloading on the C/O match the rail waybill.
Zlog tools for your shipment
Zlog cross-checks the contract, invoice, packing list, bill of lading and C/O, and flags mismatches with suggested fixes. Upload the invoice, packing list and bill of lading; Zlog splits the line items, suggests HS codes, estimates duties and exports an Excel file for ECUS.
5 steps to ship goods by international rail

Step 1: Book wagons or containers. Book with the rail carrier and confirm the departure station, border station, destination station and transshipment point.
Step 2: Specialised checks. Check whether the goods need licences, quarantine or specialised inspection in both countries. Prepare the contract, invoice, packing list, C/O and rail waybill.
Step 3: Customs declaration at the station. File the customs declaration. Inspection and clearance can be done at a domestic through station with the goods sealed, while the border station only handles the notification.
Step 4: Supervised transport. Imported goods not yet cleared at the border station are sealed wagon by wagon and carried under supervision to the destination station.
Step 5: Receive goods and clear. Take delivery at the destination station, declare freight correctly in customs value, and complete duty payment and clearance.
Practical tips
Separate the freight invoices
Do not use FOB or CIF
Match the waybill to the declaration
Frequently asked questions (FAQ)
Which border stations does international rail freight from Vietnam use?
There are currently two rail border stations, Dong Dang (Lang Son) and Lao Cai, both leading into China. Only the Dong Dang – Pingxiang route connects directly, and most other routes require transshipment.
Why does rail freight from Vietnam to China need transshipment?
Vietnamese railways use a 1,000 mm gauge and Chinese railways use a 1,435 mm gauge. The Lao Cai route has only 1 m gauge as far as Ha Khau, so goods must be moved to another train.
What is an international rail waybill?
It is a transport document issued by the rail carrier, in place of a sea bill of lading. Goods moving within the Organisation for Cooperation of Railways (OSJD) bloc use a waybill under the SMGS Agreement.
Can customs clearance be done at an inland station in Vietnam?
Yes. Goods can be inspected and cleared at a domestic through station, sealed, with only the notification handled at the border station. Imported goods not yet cleared are sealed wagon by wagon and carried under supervision to the destination station.
Which Incoterms should I use for rail freight?
Use the rules for any mode of transport, such as FCA, CPT, CIP and DAP. FOB, CFR and CIF are for sea and inland waterway transport only.
Is rail freight included in customs value in Vietnam?
International freight not already in the price actually paid must be added to customs value. Domestic freight from the interchange station to the delivery station inland is not included, under Official Letter 4838/TCHQ-TXNK of 26/7/2019.
Information checked in November 2026. Always confirm the HS code, duty rate and import rules for your specific goods against the regulations in force when you declare.
HS CODE ADVICE GROUP ON ZALO